Copyright & Fair-use Agreement
UNLV Special Collections provides copies of materials to facilitate private study, scholarship, or research. Material not in the public domain may be used according to fair use of copyrighted materials as defined by copyright law. Please cite us.
Please note that UNLV may not own the copyright to these materials and cannot provide permission to publish or distribute materials when UNLV is not the copyright holder. The user is solely responsible for determining the copyright status of materials and obtaining permission to use material from the copyright holder and for determining whether any permissions relating to any other rights are necessary for the intended use, and for obtaining all required permissions beyond that allowed by fair use.
Read more about our reproduction and use policy.
I agree.Information
Digital ID
Permalink
Details
More Info
Rights
Digital Provenance
Publisher
Transcription
4 Line No Location Date Line Became Usable 1 F Street 1 -17-56 2 Bonanza Rd. and C. St. 12-20-55 4 6th St. and Linden Ave. 1 -10-56 6 25th Street 10-11-55 17 Crestwood Dr. 11- 1-55 28 Franklin Ave. 11- 1-55 29 6th St. South of Charleston Blvd. 11- 1-55 38 17th St. at Fremont St. 1 -17-56 Although several lines became usable a considerable time before the last ones were completed, it is believed that the District is justified in assessing liquidated damages for the overtime up to the date the last lines were completed in order to reimburse the District for the additional cost of the field engineering during the long overtime period. During this period the Subcontractor failed to prosecute the work vigorously. By letter dated August 15, 1955 addressed to the District, the Contractor requested a 20-day extension. Ten days of this was for the delay at the start of the job resulting from award of the work to Pipeline Constructors first before it was awarded to the subject contractor. The other ten days was for delay caused by the heavy rains in July 1955* We recommended that this 20-day extension be granted, but the Board decided to withhold action on the extension because of the Contractors unsatisfactory progress. By letter dated January 3» 1955 (intended to be 1956) addressed to the District, the Contractor requested a 116-day extension in time. The basis for the request as outlined by the Contractor, together with our recommendations, are listed below: Item Extension Recommended No. Requested Reason Given for Delay Extension (Davs) 1 28 Period from date contract awarded to Hallmark to date subcontract with Pipeline Constructors executed----- - 10 2 20 Delay in delivery of Pipe materials due to truck strike during month of June, 1955-- 0 3 20 Delay caused by flash floods in July------- .10 4 45 Delay due to slow delivery of materials---- 0 5 3 Delay caused by change in location of pressure reducing station at 17th St. and Charleston Blvd.---------------------- 3 116 23