Please note that UNLV may not own the copyright to these materials and cannot provide permission to publish or distribute materials when UNLV is not the copyright holder. The user is solely responsible for determining the copyright status of materials and obtaining permission to use material from the copyright holder and for determining whether any permissions relating to any other rights are necessary for the intended use, and for obtaining all required permissions beyond that allowed by fair use.
Read more about our reproduction and use policy.
I agree.Information
Digital ID
Permalink
Details
More Info
Rights
Digital Provenance
Publisher
Transcription
TABULATION OF BIDS FOR THE CONSTRUCTION OF RESERVOIR AT IAS VBSAS. NEVADA ? WORK ORDER NO. 8248 Carl Way & Albert R.Eiehler J. L. AcKLand H. W. Baum Co. Iynchr Cannon Bmrr.Co. Iynoh Const. Com-nanv Sumner- Sollitt Elliott & McKenna W. A. Morrison- Bechtel Ehudsen Ryberg Sorensen H. E. Schraven Ceo. A. Whitmeyer Ss Sons Allied Cherdron Con- Const'n tractors Company Lamp sum for construction of reinforced concrete reservoir complete #32 000 $44 445 $46 000 $44 500 $36 550 $51 748 $32 800 No $36 990 $34 650 $43 126 $43 490 No $36 112 Cement furnished by Railroad Company 3 295 3 295 3 295 3 295 3 295 3 295 3 295 Bid 3 295 3 295 3 295 3 295 Bid 3 295 TOTALS $35 295 $47 740 $49 295 $47 795 $39 845 $55 043 $36 095 - $40 285 $37 945 $46 421 $46 785 - $39 407 Bardpan (Additional) - 1.10 - - - - - - - - - Excavation (Additional) - Wet 1.00 .55 2.50 5.00 2.50 3.00 1.50 1.25 1.00 3.00 3.00 6.00 ft n rn Dry .50 .45 1.00 1.00 1.00 1.50 .75 .70 .75 1.50 .75 2.50 Bardpan (Deduction) - 1.00 - - - - - - - - - - Excavation (Deduction) Wet 1.00 .45 2.00 1.00 None 2.50 1.00 .50 .60 .75 2.00 .75 tt » m Dry o lO• .40 .75 .25 .20 1.00 .50 .30 .50 .75 .75 .40 Concrete (Additional) 7.50 13.60 20.00 15.00 15.00 8.20 15.00 10,50 14.00 11.00 7.00 10.00 w (Deduction) 7.50 11.55 16.00 6.00 12.50 7.20 12.00 7.50 10.00 4.00 7.00 2.50 Time to Complete - Days 65 160 120 120 120 150 120 120 90 120 75 70 Opened By R. L. ADAMSON J. H. MARCOTTE L. P. DREW September 14, 1928 - 3:00 P.M• O f f i c e o f A s s is ta n t C h ie f E n gin eer, Los A n g e le s , C a lifo r n ia