Please note that UNLV may not own the copyright to these materials and cannot provide permission to publish or distribute materials when UNLV is not the copyright holder. The user is solely responsible for determining the copyright status of materials and obtaining permission to use material from the copyright holder and for determining whether any permissions relating to any other rights are necessary for the intended use, and for obtaining all required permissions beyond that allowed by fair use.
Read more about our reproduction and use policy.
I agree.Information
Digital ID
Permalink
Details
More Info
Rights
Digital Provenance
Publisher
Transcription
// F a cilitie s proposed by Greeley and Hansen in report dated October, 19ij-9. To Be Constructed in 1950: Transmission water main consisting o f 20” and 2” steel pipe from B.M.I. plant at Henderson, Nevada, via Pittman to 6th and Oakey Streets, Las Vegas. Booster Station No. 3 at Junction near Pittman and in sta ll 1 - Booster Pump £(30 H.P. Unit 10 MGD. Pumping Station, 6th and Oakey Street, and in sta ll k - 250 H.P. Units 10.5 MGD each. Ground Level Storage, 6th and Oakey Street, 1| MG Elevated Storage " ” ” ” 500,000 Gal. Feeder water main consisting of 30” steel pipe from 6th and Oakey Streets to 9th and Stewart Streets; l o ” steel pipe from v icin ity of Washington St. to North Las Vegas. Construct power transmission lin e and equipment. To Be Constructed in 1958: Intake structure Lake Meade including ij. - 300 HP pumping units 10 MGD each. 5V r steel pipe lin e from intake structure to intake reservoir near Lake Meade. Intake reservoir 1.0 MG capacity. Transmission water main consisting o f ij.0” steel pipe from Booster Station near intake reservoir to Junction point near Pittman. Booster Station No. 1 at intake reservoir, including 1+ - 500 HP units 10 MGD each. Remaining 3 - 500 HP units 10 MGD each and 1 - 1000 HP unit (return pump from Junction point near Pittman to B.M.I.) 8 MGD at Booster Station No. 3 at Junction near Pittman. Las Vegas Valley Water D istrict Las Vegas, Nevada