Please note that UNLV may not own the copyright to these materials and cannot provide permission to publish or distribute materials when UNLV is not the copyright holder. The user is solely responsible for determining the copyright status of materials and obtaining permission to use material from the copyright holder and for determining whether any permissions relating to any other rights are necessary for the intended use, and for obtaining all required permissions beyond that allowed by fair use.
Read more about our reproduction and use policy.
I agree.Information
Digital ID
Permalink
Details
More Info
Rights
Digital Provenance
Publisher
Transcription
% - 4 - Material handling costs: (Cont’d) LabMoorving to job Excavation Backfilling Unload and handle material Laying pipe Connecting pipe to Well No. 6 Constructing power line Construct well derriek Construct pump flange Installing pumps in wells Pour concrete foundation for derrick Cutting plates for wells Connecting pumps to new wells Install indicating and recording instruments Engineering-staking out pole and pipe lines Personal expenses Remove old 24” wood line Unloading 24” steel pipe Hauling 24” steel pipe Laying 24” steel pipe Covering 24” steel pipe Make connections to exist- in lines Cleaning up Engineering-stakes for pipe relay 15.71 628.29 69.4S 190.21 450.61 27.68 1 231.92 68306..2860 252.85 104.98 6.76 211.84 244.72 32.08 119.21 80.67 95.12 901.26 134.40 155.64 44 * 64 11.41 Contract work: Hall-Baker Exploration Co. Drill 2 wells SuHnadurlyi nigte mmse:n, tools and material Rental of digging machine Rental of owned equipment Public liability and property damage insurance Welding supplies Supplies for digging machine 3% for use of tools Hauling 24” steel pipe Replacement material: 1 1 Gate valve 24” 15 t SCH. IS.p igpoipte e2nd4” 3.79 Sto8r0e0 # eLxepaedn se 9.37&$ on 309.93.08 324.50 287.88 39.46 13.37 76.06 19.51 125.51 224.43 18.95 2.55 64.00 Investment 4 719.73 9 143.25 886.61 Operating Expenses 1 542.35 229.50 9.50 1468..2737 36.75 30299..9034 Total $32 702.97 $ 4 922.07