Skip to main content

Search the Special Collections and Archives Portal

upr000215 107

Image

File
Download upr000215-107.tif (image/tiff; 23.52 MB)

Information

Digital ID

upr000215-107
    Details

    Rights

    This material is made available to facilitate private study, scholarship, or research. It may be protected by copyright, trademark, privacy, publicity rights, or other interests not owned by UNLV. Users are responsible for determining whether permissions are necessary from rights owners for any intended use and for obtaining all required permissions. Acknowledgement of the UNLV University Libraries is requested. For more information, please see the UNLV Special Collections policies on reproduction and use (https://www.library.unlv.edu/speccol/research_and_services/reproductions) or contact us at special.collections@unlv.edu.

    Digital Provenance

    Digitized materials: physical originals can be viewed in Special Collections and Archives reading room

    Publisher

    University of Nevada, Las Vegas. Libraries

    Los Angeles, July 19, 19*46 Mr. R. L. Adamson1 Following Is the estimated percent of completion as of July 20, 19*l6, fo r Las Vegas Water F a c ilitie s , W.O. 3130: Estimated Percent of Completion Est» % Complete Estimated % of Jul y 2 °, date of Job 1946 completion Item Job 1* Reservoir 25 60 15 Aug* 30th 2* 2*4-“ Pipe Line in o l. By-pass 55 100 55 Completed % Booster Pump House & equipment 5 10 5 Aug. 30th k. Fire Pump House & Fire Lines 1 20 0*2 Sept. 30th 5* Fence — Aug. 30th 6* Well No. 11 k 100 4 Completed 7* Settling Basin 2 100 2 H 3* Power Lines 3 9° 2 .7 Aug* 30th 9* Pipe Lines in fie ld , 5 60 3*1 l Wells 10 and excluding lin e to Well #3 11 connected Line to well 9 postponed 100 «*• 61% lu n til Deo. Item 1, Reservoir. About 90^ of the concrete work has been completed, one section or 25^ of the wall and about 20% of the flo o r slab Is s t i l l to be poured. Roof framing i s about 10% complete* Roof sheathing Just arrived in Las Vegas and w ill be available when framing is completed. No roof sheathing has been placed todate* Item 3, Booster Pump House. f a Concrete flo o r slab and pump base was poured yesterday, July 13, 19*4-6. No other work completed this date. Pumps are available a t Byron-Jackson but no word has yet been received from Byron-Jackson as to date when motors w ill be shipped by the manufacturers* Item *t-, Fire Pump House and Fire Lines. Fire lin es and hydrants have been in sta lle d .