Letter discussing the leasing of water and how all involved parties were optimistic about the deal.
Text
Letter stating that damage to the pipeline was causing damage at the rail yard, and repair work should be undertaken immediately instead of waiting for scheduled maintenance.
Text
Details of pipeline maintenance including sketches of the work to be done in Las Vegas
Text
A test of the new pipeline showed that the line was beyond repair and needed replaced as soon as possible.
Text
Discussion about the repair of the pipeline and how the conditions that it operated under were responsible for its failure.
Text
Request that if the water supply going to the ice plant was to be turned off for any reason, that the ice plant be given 15 to 20 minutes warning to avoid a possible explosion.
Text
An inspection of the pipeline showed that in many places, the asphalt was coming off the pipe and there were quite a few leaks. Maintenance would allow it to last perhaps a year longer, but then it would need to be replaced.
Text
Letter describing how the pipeline from the Springs should be replaced, and how something needed to be done about the low water pressure experienced by the town when filling trains.
Text
Clark recommends replacing the sheet metal pipeline with concrete to fix a massive leaking problem.
Text
Letter from Jeffers calling attention to serious accounting problems with the Las Vegas Land and Water Company and asking for these matters to be investigated and rectified