Skip to main content
Main navigation
Finding Aids
Digital Projects
African American Experience in Las Vegas
Charles Saladino Landscape Architecture Collection
Culinary Union Photograph Collection
Dino at the Sands
Dreaming the Skyline
Entertainment
Historic Landscape of Nevada
Hoover Dam
Jamey Stillings
Menus: The Art of Dining
Nevada Test Site Oral History Project
Newspapers
Oral Histories Collection
Photograph Collections
Rebel Yell Newspaper
Showgirls
Southern Nevada: The Boomtown Years 1900-1925
Southern Nevada History in Maps
Southern Nevada Jewish Heritage Project
UNLV CSUN Records
Union Pacific Railroad Water Documents
Walking Box Ranch Collection
Welcome Home Howard
About
Request Images
Help
Provide Feedback
Special Collections Home
Search the Special Collections and Archives Portal
Search
Search
Breadcrumb
Special Collections and Archives Portal
Basic Magnesium, Inc. (BMI) Records and Photographs
Photographic prints: Album 3
Photographic prints: Album 3
Level of Description
File
Administrative Information
Language
English
Search within this collection
Inventory
Cell unit No. 4, showing chlorinator furnace shells in place and masonry crews at work: photographic negative, 1942 April 20
East view, showing construction (right): photographic print, 1942 April 20
Erection progress of structural steel roof members of cell building No. 1: photographic print, 1942 April 20
Magnesium chloride tanks (left center), rotary kiln portion of preparation (center), and tunnel kiln portion under construction (right): photographic print, 1942 April 20
Construction progress of magnesite storage silos, showing slip forms in operation: photographic print, 1942 April 20
Cell renewal building nearing exterior completion with brine storage tanks center left: photographic print, 1942 April 20
Completed application of APM siding on cell renewal building Note brine storage tanks (left): photographic print, 1942 April 15
Assembly and erection of magnesium chloride storage tanks south of preparation building: photographic print, 1942 April 15
Three 40 foot x 86 foot magnesite storage silos with truck in receiving pit under construction: photographic print, 1942 April 15
Foundations and wall forms of salt storage building: photographic print, 1942 April 15
Construction of wall forms of salt storage building: photographic print, 1942 April 15
Stripping concrete wall form to pre-heater level of rotary kiln portion of preparation building: photographic print, 1942 April 15
Vertical structural steel members in place, east half of cell building No. 1: photographic print, 1942 April 15
Showing wall forms above operating floor level, chlorine cell rectifier building No. 1: photographic print, 1942 April 15
Assembly of structural steel and rigging with P and H crane in place, chlorinator building No. 1: photographic print, 1942 April 15
Three 20 foot x 50 foot coal and salt storage silos, wall forms poured: photographic print, 1942 April 11
Brine storage tanks; showing completed raw brine tanks, first segment of 3 sludge tanks, and first segment of clariflocculator tank: photographic print, 1942 April 08
Installation of APM roofing on cell renewal building: photographic print, 1942 April 08
Cell unit No. 1, showing structural steel webbing of electrolysis floor and installation of last cell cases: photographic print, 1942 April 08
Chlorine cell buildings No. 1 erection of vertical steel members, brine, hydrogen, and chlorine piping: photographic print, 1942 April 07
Aerial view, east, of trailer camp site, and construction boarding camp: photographic print, 1942 April 07
Aerial view, south, of demountable house construction progress: photographic print, 1942 April 07
Aerial view, northwest, of magnesium plant, looking towards Royson Junction: photographic print, 1942 April 07
Aerial view, southeast, of entire plant site, looking from Royson Junction to demountable house site: photographic print, 1942 April 07
Aerial view, southeast, of entire plant site, looking from Royson Junction to demountable house site: photographic negative, 1942 April 07
Aerial view, northwest, of entire plant site with Las Vegas in background : photographic print, 1942 April 07
Showing reinforcing steel and electrical conduit in ground floor slab of No. 2 rectifier building: photographic print, 1942 April 02
Cell No. 1, showing installation of wash towers and erection of chlorination building steel frame work: photographic print, 1942 April 02
Cell unit No. 1, showing installation of cell cases and erection of steel roof members: photographic print, 1942 April 01
Aerial view, northeast, showing construction progress of cell unit No. 1: photographic print, 1942 March 31
Aerial view, east, showing construction of raw magnesite storage silos and preparation building: photographic print, 1942 March 31
Aerial view, northwest of construction boarding camp showing second unit nearing completion and ground clearing for trailer camp: photographic print, 1942 March 31
Aerial view, northwest, of entire project: reservoir (lower left), demountable house site (center right), plant site (upper right): photographic print, 1942 March 31
Aerial view, east of plant site, showing demountable houses (upper right) and construction boarding camp (upper center): photographic print, 1942 March 31
Aerial view, east of plant site, showing demountable houses (upper right) and construction boarding camp (upper center): photographic negative, 1942 March 31
Aerial view, northwest, showing construction progress of demountable houses: photographic print, 1942 March 31
West basin of the terminal reservoir showing gunite operations in progress: photographic print, 1942 March 30
Cell unit No. 1, showing installation and painting of cell cases and steel structure: photographic print, 1942 March 28
Electrical conduit and reinforcing steel installation on ground floor deck of rectifier section of cell building No. 1: photographic print, 1942 March 28