Please note that UNLV may not own the copyright to these materials and cannot provide permission to publish or distribute materials when UNLV is not the copyright holder. The user is solely responsible for determining the copyright status of materials and obtaining permission to use material from the copyright holder and for determining whether any permissions relating to any other rights are necessary for the intended use, and for obtaining all required permissions beyond that allowed by fair use.
Read more about our reproduction and use policy.
I agree.V 2* Mr* R.L® Adamson: Item 4, Fire Pump House and Fire Lines ( Contd.) Fire pump base has been placed but no other work completed on pump house except forms fo r floor* The la s t advice from Worthington Pump Co* is that the fi r e pump is scheduled to be shipped from Harrison, N*J* on August 31st* Item 9> Power Lines* Power lin e has been completed to Pump House site* Information from Store Dept* indicates that transformers have been promised fo r shipment from the factory on July 1 5 , 1946. G E N E R A L : Mr* Pegraa, Supt* fo r McNeil Housing, was instructed yesterday, July ISth, to place top on valve box Just west of U* P* main lin e and also replace barb wire fence along the Wollman property and along 0*P* right-of-w ay. He was also instructed to replaoe 2 posts in Opaco Lumber Co* fence which were removed at time ditch was dug under fenoe* L • R • J