Please note that UNLV may not own the copyright to these materials and cannot provide permission to publish or distribute materials when UNLV is not the copyright holder. The user is solely responsible for determining the copyright status of materials and obtaining permission to use material from the copyright holder and for determining whether any permissions relating to any other rights are necessary for the intended use, and for obtaining all required permissions beyond that allowed by fair use.
Read more about our reproduction and use policy.
I agree.LEE CONSTRUCTION CO., IMG. CA (NLP-2590) DATED JUNE 21-1952 RID&EVIEW TRACT MO 5 Work Completed - June 26-1952 - WO 698 Cost to Subdivider - Subject to Refund Refund - 35$ of Revenue To and including June 1952 Balance of cost subject to refund Anticipated Revenue • (Based on current rates during term of Contract - 119 months) 3 Units % $2.25 - 119 months $803.25 6 Units <§> 2.25 - 11? months 1579.50 6 Units @ 2.25 - 114 months 1539*00 6 Units @ 2.25 - 111 months 1498>50 $5420.25 Estimated portion refundable Assuming $1897.09 refunded in equal monthly instalments during balance of term of Contract (119 months) monthly payment would be: Present worth of $15.94 for 119 months at 6% per annum: $15.94 X 89.524 Discount - 25$ Purchase Price Proof Monthly payment, necessary to pay off present worth $1427.01 in 119 monthly instalments including 6% interest on deferred balance - $1.1170 per $100 $5851.20 none $5851.20 $1897.09 $ 15.94 $1427.01 356.75 $ 1070.26 $ 15.94